What should be in a professional AV installation quote

Labelled equipment rack after commissioning
In this guide
  1. Scope, stated as outcomes
  2. Exclusions, written down
  3. Drawings and documentation
  4. Testing and commissioning
  5. Training and handover
  6. Support after handover
  7. Comparing two bids

Comparing AV quotes is difficult because the expensive parts are often the parts nobody writes down. This is what a complete quote contains, and how to compare two that look very different.

Scope, stated as outcomes

An equipment list is not a scope. It says what will be delivered to site, not what will exist when the job is finished. A proper scope describes what each room will do.

Weak

Eight in-ceiling speakers, one amplifier, one controller.

Better

Four audio zones: kitchen, great room, primary suite, patio. Each independently controllable from keypad and app, levels calibrated at handover.

Control processor and touch panel
Control processor and touch panel

Exclusions, written down

What is not included matters as much as what is. Unstated exclusions become change orders.

Exclusions a quote should address explicitly
  • Mains electrical work and who holds that licence
  • Patching, painting and making good after cable routing
  • Builder work such as blocking, backboxes and pockets
  • Network service from the provider
  • Furniture, millwork and mounting substrate
  • Anything contingent on another trade finishing first

Drawings and documentation

On anything beyond a single room, drawings should be part of the deliverable: a rack elevation, a signal flow, and a plan marking device locations. These are what make the system maintainable and what let you compare one proposal against another meaningfully.

If nobody drew it, nobody can check it, and nobody can maintain it.

Testing and commissioning

This is the line item most often missing and most often the difference in price.

Commissioning that should be itemised
  • Certification results for every network run
  • Audio levels set per zone, measured rather than estimated
  • Display and projector calibration
  • Every scene and every source tested
  • Camera views checked at night as well as during the day
  • Control tested by someone who did not program it

Training and handover

A system nobody can operate is not finished. Handover should include a session with the people who will use it, in the house or the office, with the system live, plus something written to refer back to.

Support after handover

Ask what happens when something stops working six months later. Specifically: response time, what is covered, what is billable, whether remote support is included, and who to contact. A quote that is silent on support is quoting an installation, not a working system.

Comparing two bids

If one quote is cheaper, checkWhy it matters
Is commissioning included?Often the whole difference
Are drawings included?Affects maintainability for years
Who patches and paints?Can become a significant separate cost
Is cable certified or just connected?Determines whether faults appear later
Is training included?Decides whether the system gets used
What support follows?Decides what happens when something breaks
A fair way to compare

Send both companies the same written scope and ask them to price that, rather than asking each for a proposal. Two responses to one scope are comparable. Two independent proposals usually are not.